Resources, periods, capacity, and demand

Build a unit-consistent resource ledger in which every capacity and demand cell has a period and provenance.

EnglishEspaƱolFranƧais

Documentation follows the current system language. Missing translations fall back to the page's canonical language.

Resources, periods, capacity, and demand

Define ordered periods at the resolution the decision can credibly support. Define each constrained resource separately—capital dollars, design hours, lane-closure nights, specialized crews, concrete-plant throughput, equipment, or facility slots—and assign one unambiguous unit. Never add unlike units or substitute nominal headcount for available hours.

For every resource-period cell, record usable capacity after existing commitments, reserves, maintenance, calendars, and policy restrictions. For every initiative-resource-period cell, record incremental demand on the same basis. Each numeric cell needs a basis, evidence identifiers, or an explicit assumption flag. Zero means known zero; blank means unknown. Missing required cells make analysis incomplete rather than silently contributing zero.

Avoid false precision. Use the coarsest periods and units that remain decision-relevant, document whether capacity carries forward, and model seasonal or mobilization limits explicitly. Scenario overrides should explain why the capacity changes; they do not rewrite the baseline.

Illustrative capacity, demand, and slack

Illustration only: capacity 100, selected demand 84, slack 16. Values are not forecasts or reusable defaults; each real cell needs a unit, period, and provenance.

Next: candidates, evidence, and uncertainty.

References

PMI — The Standard for Portfolio Management, Fourth Edition

Portfolio-management guidance connecting strategy, component selection, resource supply and demand, value, and governance.

https://www.pmi.org/standards/for-portfolio-management

Solving a comprehensive model for multiobjective project portfolio selection

Research on multiobjective project-portfolio selection with multiple periods, resource constraints, and project interdependence.

https://doi.org/10.1016/j.cor.2009.06.012